- Same 2022–23 plan
- Golden Pacific and the canceled Serrano line were approved in the same CAISO cycle
- $5B → ~$50M
- A 500 kV line was scrapped; a small upgrade to an existing line met the leftover need
- Re-tested yearly
- The grid operator re-runs the cost-effectiveness math every planning cycle
A line can die without a fight
The “Stopped Before” precedents are all adversarial: a line denied by the regulator, withdrawn under community pressure, or forced underground. There's a quieter way a line dies — the grid operator that planned it re-runs the numbers and cancels it itself, because something cheaper now meets the same need. No lawsuit, no denial, no protest; just an updated spreadsheet. [1]
And it's not rare. California's grid operator doesn't approve a transmission plan once and walk away — it rebuilds the plan every year, and projects blessed in one cycle are routinely re-scoped, delayed, or canceled in a later one as costs rise and alternatives improve. A line approved today is a line re-tested next year. [2] [1]
The case study: a 500 kV line that canceled itself
In its 2022–2023 plan — the very plan that approved Golden Pacific — CAISO greenlit the Serrano–Del Amo–Mesa project: a major new 500 kV reinforcement for the Los Angeles Basin, estimated at about $1.1 billion and assigned to Southern California Edison to build. [3]
Then two things happened. As SCE took the project into detailed engineering, its own cost estimate ballooned to $5.0 billion — more than four times the approved figure. And the reason for the line quietly evaporated: the state's latest resource plans already placed roughly 2,000 megawatts of battery storage downstream of the bottleneck the line was meant to relieve, so it was no longer needed to move renewable power. [4]
So in the 2025–2026 plan, CAISO canceled it. And what replaced a five-billion-dollar line? Almost nothing, by comparison. The renewable-deliverability problem was already solved by that storage. The only leftover reliability need is handled by a single small project — reconductoring 4.9 miles of the existing Mesa–Laguna Bell 230 kV line with a higher-capacity advanced conductor, at about $41–56 million, in service by 2032, sized specifically so those batteries can charge. Storage already in the plan, plus one cheap upgrade to a line that already exists. [4]
Sit with that. A 500 kV line, approved and scheduled, erased from the plan — not by opponents, but by its own planner, because storage and a modest upgrade to the existing grid did the same job for a hundredth of the cost and a fraction of the footprint. That is the alternatives section of this site, playing out for real. [4]
- As approved (2022–23)$1.1B
- Re-estimated in engineering · SCE's own number — why it was canceled$5.0B
- The upgrade that replaced it · + storage already in the state's plans~$50M
CAISO approved the Serrano 500 kV line at $1.1B in 2022–23; by detailed engineering SCE's own estimate had reached $5.0B, so the grid operator canceled it. The renewable-deliverability need had already been dissolved by ~2,000 MW of batteries in the state's resource plans, leaving a reliability sliver met by a single ~$41–56M reconductoring of an existing 230 kV line. [4]
Could it happen here?
The honest answer: the exact mechanism that canceled Serrano is live for Golden Pacific right now. The two lines were approved in the same 2022–2023 CAISO plan; CAISO re-tests that plan every year; and it has already canceled one of the two. [6] [1]
Golden Pacific's own cost isn't even settled. SDG&E is still developing the figure — a working range today, with the official number not due until its CPUC application in late 2026. [7] And Serrano is a warning about exactly that: its price more than quadrupled — from about $1.1 billion to $5 billion — once engineers looked closely. [4] Every cost increase, and every cheaper alternative that proves out, moves Golden Pacific toward the line Serrano crossed. The cost-effectiveness test that killed the sibling project is wide open here.
Be clear about what this is not: it's not a prediction that the line will quietly cancel itself. SDG&E is actively pushing it, and it carries a policy-driven, move-the-renewables justification Serrano didn't. [5] A self-cancellation is the opposite of passive — it only happens if the cheaper alternatives are credible and on the record when CAISO re-runs the math.
What tips the math — the alternatives are the ingredients
That's why everything else on this page matters. The portfolio that replaced Serrano — storage plus reconductoring — is exactly what's laid out in Upgrade the lines we already have. Pair it with local solar and storage near the coastal load, and the weak local-need case in Is a new line even needed?, and you assemble the same kind of cheaper-than-the-line package CAISO chose in the LA Basin. [1]
No single alternative has to “win” outright. They combine. Each cheaper option that gets studied and proven shrinks the gap until the big line is no longer the rational choice — and the planner's own cost-effectiveness rules do the rest. The job of opposition isn't only to fight the line; it's to put the cheaper answer on the record before the next re-evaluation.
Read it honestly
A self-cancellation is a mechanism, not a guarantee. It depends on updated costs landing the wrong way for the line, on the alternatives being credible and documented, and on a planner willing to act on them. CAISO did exactly that for Serrano; whether it does the same here depends on the facts built between now and the next planning cycle. Documenting the alternatives is how you make sure those facts exist when the question is asked. [1] [2]
Go deeper
Sources
- [1]CAISO 2025-2026 Transmission Plan — cancels the Serrano–Del Amo–Mesa 500 kV line — California ISO / Utility Dive
- [2]Grid-enhancing technologies & reconductoring as transmission alternatives — CAISO / Utility Dive / GridLab (2035 Report)
- [3]Serrano–Del Amo–Mesa 500 kV Transmission Reinforcement — approved (2022-2023) scope & ~$1.1B cost — California ISO (CAISO)
- [4]CAISO Board-Approved 2025-2026 Transmission Plan — Serrano cancellation, $5.0B re-estimate & the replacement — California ISO (CAISO)
- [5]CAISO Board-Approved 2022-2023 Transmission Plan — CAISO
- [6]CPUC Docket R.22-11-013 exhibit SEIA-03 (CAISO plan excerpt) — CPUC
- [7]SDG&E says its proposed transmission line would meet growing power demand, but opposition is growing — KPBS